Project Location

2927 N Irving Ave, Minneapolis, MN 55411

Location Map

Project Manager

Crystal Passi
Phone: 612-230-6455
Email: cpassi@minneapolisparks.org

Subscribe to Email Updates

Language Resources

Correo Electrónicopreguntas@minneapolisparks.org

Emailsuaalo@minneapolisparks.org

Construction Update

Work by construction crews will continue at Jordan Park through fall for as long as weather allows. After a pause for winter, crews will resume work next spring. The park’s […]

Construction on Jordan Park’s new wading pool, other improvements begins soon!

The Minneapolis Park and Recreation Board (MPRB) is pleased to announce that construction begins in late May on the project bringing a new wading pool and other improvements to Jordan […]

The existing wading pool at Jordan Park will open this weekend 8/6/22

The existing wading pool at Jordan Park will open this weekend (August 6th) for the remainder of the summer. It has been closed until this point due to mechanical issues. […]

Construction on Jordan Park improvements, along with others park projects, is temporarily delayed

The Minneapolis Park and Recreation Board (MPRB) recently announced temporary construction delays for improvement projects at Hall and Farwell parks due to high construction bids. Unfortunately, construction is also temporarily delayed on Jordan Park‘s wading pool […]

Jordan Park Pool Improvements – Concept Plan

The concept plan for Jordan Park was approved by the board of commissioners on November 17th, 2021. The project team will further develop the plans and the project will be […]

Improvements are coming to Jordan Park!

Open House for Pool Improvements on August 31st The Minneapolis Park & Recreation Board (MPRB) is pleased to announce an improvements project at Jordan Park in North Minneapolis. The project includes replacing […]

Milestones (anticipated project schedule by month/season)

Engagement & Design

2021

Construction

May 2023-Spring 2024

Subscribe to Email Updates

Enter your email to receive updates about meetings, events and more.

Upcoming Meetings

There are no upcoming meetings scheduled at this time.

Background

This project will begin a first phase of implementation of priority projects identified during the North Service Area Master Planning Process (NSAMP). This first phase of park improvements will consist of replacing the existing pool, pool mechanical building, pool site amenities and adding restrooms at Jordan Park. Design and engagement will occur throughout 2021 with construction to occur in 2023 & 2024. Visit the North Service Area Master Plan project page for more information about the planning for Jordan Park.

Funding sources and park history

This project will begin a first phase of implementation of priority projects identified during the North Service Area Master Planning Process (NSAMP). This first phase of park improvements will consist of replacing the existing pool, pool mechanical building, pool site amenities and adding restrooms at Jordan Park. Design and engagement will occur throughout 2021 with construction to occur in 2022. Visit the North Service Area Master Plan project page for more information about the planning for Jordan Park.

The total budget for Jordan Park Improvements is $1,695,434.00. This funding will go towards staff and consultant time, design, and construction. Funding is allocated from the following sources:

NPP20: $1,620,000
Park Dedication: $75,434