Jordan Park Improvements Includes replacing the pool and mechanical building and adding restrooms, based on the park's approved master plan

Project Location

Jordan Park
2927 N Irving Ave, Minneapolis, MN 55411

Location Map

Project Manager

Crystal Passi
Phone: 612-230-6455
Email: cpassi@minneapolisparks.org

Subscribe to Email Updates

Language Resources

Correo Electrónico: preguntas@minneapolisparks.org
Email: suaalo@minneapolisparks.org

Help make a mural for Jordan Park and learn about the Mississippi Flyway

Two FREE workshops at Northside parks! Friday June 20, 4-7pm & Saturday, June 21, 1-4pm Everyone is invited to help create an enamel mural for Jordan Park at two free, […]

Jordan Wading Pool and Restroom Building Now Open!

The new wading pool at Jordan Park is open and ready for fun! Construction on the new wading pool began last year and has continued this spring. Construction crew’s and […]

Construction Update

Work by construction crews will continue at Jordan Park through fall for as long as weather allows. After a pause for winter, crews will resume work next spring. The park’s […]

See All Project Updates

Milestones (anticipated project schedule by month/season)

Engagement & Design

2021

Construction

May 2023-Spring 2024

Subscribe to Email Updates

Enter your email to receive updates about meetings, events and more.

Upcoming Meetings

There are no upcoming meetings scheduled at this time.

Background

This project will begin a first phase of implementation of priority projects identified during the North Service Area Master Planning Process (NSAMP). This first phase of park improvements will consist of replacing the existing pool, pool mechanical building, pool site amenities and adding restrooms at Jordan Park. Design and engagement will occur throughout 2021 with construction to occur in 2023 & 2024. Visit the North Service Area Master Plan project page for more information about the planning for Jordan Park.

Funding sources and park history

This project will begin a first phase of implementation of priority projects identified during the North Service Area Master Planning Process (NSAMP). This first phase of park improvements will consist of replacing the existing pool, pool mechanical building, pool site amenities and adding restrooms at Jordan Park. Design and engagement will occur throughout 2021 with construction to occur in 2022. Visit the North Service Area Master Plan project page for more information about the planning for Jordan Park.

The total budget for Jordan Park Improvements is $1,695,434.00. This funding will go towards staff and consultant time, design, and construction. Funding is allocated from the following sources:

NPP20: $1,620,000
Park Dedication: $75,434