New Nicollet Park Potential acquisition and development of a new park on the former Kmart Site at Nicollet Avenue and Lake Street

Project Location

10 West Lake Street, Minneapolis, MN 55408

Location Map

Project Manager

Colleen O’Dell
Phone: (612) 230-6469
Email: codell@minneapolisparks.org

Subscribe to Email Updates

Language Resources

Correo Electrónico: preguntas@minneapolisparks.org
Email: suaalo@minneapolisparks.org

Key Documents

Status

Current Phase: System Planning
Anticipated Construction Timeframe: 2025+

The City of Minneapolis is seeking development proposals for New Nicollet Phase 1

The City of Minneapolis (“City”) is looking for developers with creative and community-focused ideas to redevelop the first phase of the New Nicollet site, formerly home to Kmart. The City opened a request for proposals (RFP) for Phase 1 of the project at Lake Street and Nicollet Avenue on Oct. 6, […]

New Nicollet (Former Kmart Site) Survey Open Through November 8

MPRB staff are in consultation with the City of Minneapolis to potentially add a new public park to a 10-acre redevelopment site owned by the City on Lake Street. The City […]

Milestones (anticipated project schedule by month/season)

Summer 2025 – anticipated construction of a reconnected Nicollet Avenue road and bridge from Lake St to Cecil Newman Lane

2026 – anticipated conveyance of land from city to MPRB for new park

2028 – anticipated community engagement and concept design of a New Nicollet Park, with construction possibly beginning the following year

History

2018 – City purchased Kmart site following the company’s bankruptcy

2021 – Collaborative project discussions began between City and MPRB to include a public park with housing and commercial development at the site

2022 – City launched New Nicollet Redevelopment project including community engagement, cost estimates, and design concept exploration

Nov 2023 – Kmart demolition completed

May, 2024 – MPRB and City Council approved an MOU outlining cooperative intent to create a new park on a portion of the former Kmart site at 10 West Lake Street.

Subscribe to Email Updates

Enter your email to receive updates about meetings, events and more.

New Nicollet Developer/Non-Profit Mixer Event
October 22, 2025
4-5:30 pm
Centro Nicollet (2412 Nicollet Ave., Minneapolis, MN 55404)

Interested site developers/non-profits can meet the project team and ask questions.

Background

The City of Minneapolis owns approximately 10 acres of land between the Midtown Greenway, Lake Street, 1st Avenue, and Blaisdell Avenue. This property is referred to as “New Nicollet (former Kmart) site.” The City plans to reconnect and reconstruct Nicollet Avenue between 29th Street and Lake Street, and to develop a high-density, mixed-use, walkable district on the rest of the city-owned site.

MPRB adopted the Southwest Service Area Master Plan in 2020. This plan identifies a need to acquire additional public parkland within a “park search area” that includes the Whittier neighborhood. The New Nicollet site is also located in this park search area. Both the City and MPRB have been in consultation since 2021 about conveying part of the site for parkland, and both wish to work collaboratively to create a new park at this location.