28th Street Tot Lot Park Improvements Project This project will re-design and construct park landscape, play and skateboard improvements. The design for this park will be guided by the park's Master Plan and community engagement

Project Location

28th Street Tot Lot Park
175 E 28th Street
Minneapolis, MN 55408

Location Map

Project Manager

Carol HejlStone
Phone: 612-230-6454
Email: phejlstone@minneapolisparks.org

Subscribe to Email Updates

Language Resources

Status

Current Phase: Complete
Construction Timeframe: Fall 2024/Spring 2025

Key Documents

New date! 28th Street Totlot Ribbon Cutting on August 14 at 6pm

Join us to cut the ribbon on recently completed park improvements! Thursday, August 14 6pm ribbon cutting followed by ice cream social at 6:30 pm 28th Street Totlot, 175 East 28th […]

POSTPONED: 28th Street Totlot Grand Opening Celebration Saturday, June 14

THIS EVENT WAS POSTPONED IN RESPONSE TO THE TRAGIC, TARGETED SHOOTINGS OF MINNESOTA STATE LAWMAKERS ON JUNE 14. NEW DATE IS TO BE DETERMINED. After its closure for years during […]

Construction of park improvements at 28th St Tot Lot soon to be underway

The Minneapolis Park and Recreation Board (MPRB) is pleased to announce that it is moving forward on the improvements project at the park known as the 28th Street Totlot. Construction of […]

Survey: 28th Street Tot Lot Park Improvements and Park Naming

Please take this survey to help MPRB staff and City of Skate representatives know your thoughts about park concept and feature plans. The survey is live through Friday, March 10. […]

Help us design 28th Street Tot Lot Park!

The Minneapolis Park & Recreation Board (MPRB) is pleased to announce a project to restore and improve the 28th Street Tot Lot Park to align with recommendations in the park’s […]

See All Project Updates

2023

Community Engagement and Concept Design

Winter 2023/2024

Final Design

Spring 2024

Bidding

Fall 2024/Spring 2025

Construction

Subscribe to Email Updates

Enter your email to receive updates about meetings, events and more.

Upcoming Meetings

There are currently no meetings planned.

Project History

2017 – Aging play equipment was demolished and the site became a staging area for the major I-35W re-construction project

2017 – Skate Park Activity Plan Approved

2020 – Southwest Service Area master Plan Approved

2022 – I-35W Project Construction Complete

2022 – MPRB and MnDOT Begin Land Acquisition Process for 28th St Tot Lot Site

Funding

28th St Tot Lot Park was allotted $200,000 in CIP (Capital Improvement Project) funding for park improvements and currently represents the total budget for the project. This funding will go towards staff, consultant time, community engagement, design, and construction.

MPRB staff will collaborate with MnDOT for park landscaping and City of Skate for skatepark improvements. MPRB staff will continue to seek funding and partnership opportunities throughout the project