Status
Current Phase: Construction at Nokomis; Bid Award and Summer Construction for Loring
What's New
New dedicated outdoor pickleball courts open at Dickman and Loring Parks this fall
New courts also opened at Lake Nokomis earlier this summer
Celebrate new outdoor pickleball courts next to Lake Nokomis Community Center on July 12!
First dedicated outdoor pickleball courts in Minneapolis park system are open
Nokomis Pickleball courts are on track to be completed early this summer
The Nokomis Pickleball courts are on track to be completed by early June this year. The main work that is remaining is the final court surface which needs consistent 50 […]
Timeline
Anticipated Project Schedule
Fall 2021 – Winter 2022: Community engagement
Winter 2022: Board of Park Commissioners approves amending park master plans to include pickleball
Fall 2022 – Spring 2023: Conversion of two tennis courts next to Lake Nokomis Community Center into six pickleball courts
Fall 2022: Pickleball striping added to tennis courts along on Minnehaha Parkway Regional Trail
Winter 2022-23: Design and bidding for two new pickleball courts at Loring Park, next to the newly renovated tennis courts.
Summer 2023: Construction of two new pickleball courts at Loring Park
Get Involved
Subscribe to Email Updates
Enter your email to receive updates about meetings, events and more.
Upcoming Meetings
No upcoming meetings
History
The three master plans were amended by the Board of Commissioners in 2022. Adoption dates and links to each master plan are below:
- Loring Park Master Plan (part of the Downtown Service Area Master Plan): adopted November 2017
- Minnehaha Parkway Regional Trail Master Plan: adopted November 2020
- Nokomis-Hiawatha Regional Park Master Plan: adopted March 2015 and amended August 2017