Updated Project Scope

While planning the first two phases of improvements for Northeast Park, field/path improvements and a new recreation building, MPRB encountered project costs that exceeded the budgets for both projects. Based on community input, MPRB staff recommended re-allocating funding from the fields project to the new recreation building. The two softball fields scheduled to be re-constructed this fall will be placed on the hold, and the remaining funding for the fields will be put toward path and restroom improvements on the east side of Fillmore Street.

The path and restroom improvements on the east side of Fillmore Street are in design right now and are planned to be under construction in 2016.