The following improvements are scheduled for Bossen Field Park as part of some of the Phase One Master Plan improvements.

New Water Service:

Installation of the new water service line to the park building is almost complete. The work began in mid-May and is scheduled to be completed early June. The new water service line replaces the existing water service line which had degraded. The new water service will provide a more reliable water source to operate the wading pool and park building.

Building Improvements:

The park building improvements which commenced Fall 2018 are now complete. Some of the new building improvements updated the existing bathrooms with new fixtures and lighting and added a new ADA compliant All-Gender bathroom. The lighting around the park building was upgraded with LED light fixtures and building security systems were installed to help with the operation of the park building.

Softball Field Dugout Covers:

New dugout covers are scheduled to be installed in the coming weeks at each player dugout for the 6 new softball fields. The new dugout covers will be great additions to the new softball fields, providing players with shade and shelter from the elements.


Back to Project Page