Project Location
Location MapProject Manager
Jon Duesman
Phone: 612-230-6471
Email: jduesman@minneapolisparks.org
Link to Bassett Creek Watershed Management Commission Project Page
Bassett Creek Main Stem Lagoon Dredging ProjectSubscribe to Email Updates
Language Resources
Correo Electrónico: preguntas@minneapolisparks.org
Email: suaalo@minneapolisparks.org
Key Documents
Status
Current Phase: Research & Development
What's New
Bassett Creek Dredging Feasibility Study
The proposed project will remove sediment that has collected in three of the seven lagoons (D, E and F) created along the Main Stem of Bassett Creek in Wirth Park, […]
Timeline
Project Milestones
Develop concept alternatives and cost estimates: Winter 2019 – January 2020
Public engagement: February 2020
Submit draft feasibility report: March 2020
Regulatory agency review: March 2020
BCWMC review: April – May 2020
Final Feasibility Report: May 2020
Get Involved
Subscribe to Email Updates
Upcoming Meetings
Background & Funding
Background
Funding
As is required for Bassett Creek Watershed Management Organization (BCWMC) CIP Projects, a feasibility study must be completed prior to BCWMC holding a hearing and ordering the project. The feasibility study will estimate the amount of material to be dredged, identify sediment contamination issues, discuss methods for dredging the material from the lagoons and disposing of the dredged material, review the environmental review and permitting requirements, and develop a concept plan and cost estimate for the project.
This project is consistent with the goals and policies in the 2015 – 2025 BCWMC Watershed Management Plan. The BCWMC completed a Resource Management Plan (RMP) in 2009 through which the USACE and the BCWMC agreed on a series of steps, work items, deliverables (called “protocols”) that must be accomplished and submitted to complete the RMP process and USACE review/approval process.
Several studies and projects have been completed in and along the study area.
Relevant work and scope implications are listed below:
- Feasibility Report for the 2012 Bassett Creek Main Stem Restoration Project – Golden Valley Road
to Irving Avenue North (Barr, 2011)