North Commons Park Improvements A transformative, once-in-a-generation project to create a Northside hub for arts, recreation, athletics and community activities, with new waterpark, three-gym fieldhouse and renovated community center.
Project Location
North Commons Park
1801 N James Ave
Minneapolis, MN 55411
Project Managers
Daniel Elias
Phone: 612-230-6435
Email: delias@minneapolisparks.org
Adam Arvidson
Phone: 612-230-6470
Email: aarvidson@minneapolisparks.org
Subscribe to Email Updates
Language Resources
Correo Electrónico: preguntas@minneapolisparks.org
Email: suaalo@minneapolisparks.org
Status
Current Phase: Construction
Time Frame: Project will be completed in phases in 2026 and 2027
Key Documents
See also “Project Documents” tab below
Community Engagement
- North Commons Community Engagement Plan – Update [PDF]
- North Commons Community Engagement Assessment [PDF]
- North Commons Community Engagement Plan [PDF]
Transforming North Commons Park: Combating Health Wealth Disparities (April 2024) [PDF]
February 2025: Aerial View | North Entry | James Ave. View | East View | South Entry
February 2024: Aerial View | Aerial View – Winter | North Plaza | South Plaza | Entry Lobby looking South | Fieldhouse looking North | Fieldhouse from Track | Multipurpose Room | Craft Room | Existing Gymnasium | Lounge | Entry Lobby looking West | Wellness Room | Water Park Activity Area | Water Park Aerial View | Water Park Lap Pool View
What's New
April Construction Update
Construction is 40 percent complete! The Minneapolis Park and Recreation Board (MPRB) is making a historic investment to expand and transform facilities at North Commons Park. When completed, the park’s northeast corner […]
March Construction Update
Construction is 35 percent complete! The Minneapolis Park and Recreation Board (MPRB) is making a historic investment to expand and transform facilities at North Commons Park. When completed, the park’s northeast corner […]
February Construction Update
Construction is 25 percent complete! The Minneapolis Park and Recreation Board (MPRB) is expanding and transforming park facilities at North Commons Park. When completed, the park’s northeast corner will include a new […]
Timeline
- June 2025 – June 2027: Construction
- 2025 January – May: Bidding and Construction Contract Award
- 2023 (November) – 2024 (December): Detailed Design
- 2023
- October : Concept Design Approved by Board of Commissioners
- April: Community and Board Update on concept design status
- 2022: MPRB submits a second request for state bonding
- 2021 (September) – 2023 (March): Programmatic design, concept design and feasibility analysis, with cost estimates, including continued community engagement
- 2021 July-September: Initial general community engagement
- 2021 June-August: Completion of Community Engagement Plan, issuance of consultant RFP, selection of consultant
- 2020: State of Minnesota awards MPRB $5 million in state bonding (of a $11 million request) for the North Commons Project, to go along with $1.8 million of NPP20 funding allocated by MPRB
- 2019: North Service Area Master Plan–including plan for North Commons Park–adopted by Board of Commissioners
- 2017: MPRB begins a community-engaged process to create new park plans for every park in North Minneapolis
Project Documents
June 2025: Construction Contracts – Initial Awards
November 2024: Contracting Goals and Methods: Board Meeting
August 2024: Amendment for 2026 Capital Improvement Program (CIP) reallocating $10.3 million in 2026 CIP funds to the North Commons Park improvements project
- Staff Presentation on Amendment to Admin & Finance Committee [PDF]
- Admin & Finance Committee Meeting [Video]
- News Update
September 2023: Concept Design Public Hearing on Draft Preferred Concept Designs
- Presentation by MPRB Staff [PDF]
- September 2023 Board Meeting [Video]
- Public Hearing/Comments [Video]
- Planning Committee Discussion [Video]
September 2023: Draft Preferred Concept Designs
- North Commons Park Phase 1 Improvements Draft Preferred Concept Designs [PDF]
- North Commons Park Phase 1 Improvements Draft Preferred Concept Designs (with Appendix) [PDF]
April 2023: Study Report
- April 26, 2023 Board Study Report Presentation [PDF]
- Concept Design Options – Complete Engagement Results [PDF]
- April 26, 2023 Board Study Report (Video)
- April 25, 2023 Study Report Public Preview Meeting Notes [PDF]
Concept Options
- North Commons Park Concept Design Options [PDF]
- North Commons Park Concept Design Options (condensed) [PDF]
- North Commons Park Concept Design Options Video Walkthrough
Playground Concept Design
Project Background Info
- North Service Area Long-Range Vision Plan [PDF]
- Handout: North Commons Long-Range Vision Plan and Guiding Principles [PDF]
- Fact Sheet: North Commons Improvements [PDF]
Community Engagement
- North Commons Community Engagement Plan – Update [PDF]
- North Commons Community Engagement Assessment [PDF]
- North Commons Community Engagement Plan [PDF]
- North Commons Community Engagement Flyer [PDF]
- North Commons Design Week Flyer [PDF]
- Community Engagement Summary (Oct 2022) [PDF]
- Community Engagement Summary with Appendix (Oct 2022) [PDF]
Initial Open Houses
2022 Community Collaborators
- Latora Powers – Sunday, August 21st, 2-5pm
- Kamilla El-Amin/KNE Resource – TBD
- Keiona Cook/Lovely’s Sewing and Arts Collective – Tuesday, August 16th, 2-3:30pm
- One Family One Community – Saturday, August 20th, 2-5pm [PDF]
- Masjid An-Nur – TBD
Funding
Funding status (updated December 2025)
$12.2 million MPRB funds
$20.5 million Minneapolis Parks Foundation fundraising commitment from its current Transforming North Commons Park campaign
$10.9 million State and Federal funds and other grant funds
$43.6 million Total
MPRB is confident about the options for securing the remaining funds for the $49 million project
Get Involved
Subscribe to Email Updates
Enter your email to receive updates about meetings, events and more.