Cedar Avenue Field Park Improvements Project Phase 1 Improvements Project for Cedar Avenue Field Park
Project Location
Cedar Avenue Field Park
2500 Cedar Ave.
Minneapolis, MN 55404
Project Manager
Carol Hejlstone
Phone: 612-230-6454
Email: phejlstone@minneapolisparks.org
Subscribe to Email Updates
Language Resources
Correo Electrónico: preguntas@minneapolisparks.org
Email: suaalo@minneapolisparks.org
Key Documents
- Cedar Avenue Field Design – 3D Renderings [PDF]
- Final Cedar Avenue Field Park Designs [PDF]
- What we have heard board – Cedar Avenue Field Park [PDF]
Status
Current Phase: Pre-Design
Anticipated Construction Timeframe: Playground 2026, Sitework 2027
Road Closures: No
NPP20 Funded: Yes
What's New
Cedar Field Park Blessing and Tree Walk
The phase 1 project to begin implementation of the recently approved long range vision plan for Cedar Field Park is underway! Join us (rain or shine) at Cedar Avenue Field […]
Timeline
Milestones
- New Playground installation – Summer/Fall 2026
- Complete Construction Documents – Summer/Fall 2026
- Sitework Construction – Spring through Fall 2027
- Park Tree and Understory Plantings – Spring 2028
Get Involved
Subscribe to Email Updates
Enter your email to receive updates about meetings, events and more.
Upcoming Meetings
Cedar Avenue Field Park Blessing and Tree Walk
November 6, 2025
3:30 pm
Cedar Avenue Field Park
The next step in the Cedar Field Park Project is to bless the ground and to identify which trees are sacred to community. Please join us for an activity designed for you to tell us which trees are important to you. There will also be an activity for kids to help choose what playground equipment types they like best.
Background
Background
Park Board Announcements
There are no announcements at this time. Please check back soon.