Bde Maka Ska Shoreline Repairs MPRB will be reviewing environmental issues contributing to increased shoreline instability to help with developing planned improvements to repair and stabilize the shoreline along the west side of Bde Maka Ska.
Project Location
3000 Bde Maka Ska Parkway
Minneapolis, MN 55408
Project Manager
Jon Duesman
Phone: 612-230-6471
Email: jduesman@minneapolisparks.org
Subscribe to Email Updates
Language Resources
Correo Electrónico: preguntas@minneapolisparks.org
Email: suaalo@minneapolisparks.org
Key Documents
Status
Current Phase: Pre-Design
Anticipated Construction Timeframe: 2026/2027
Road Closures: No
NPP20 Funded: No

What's New
Bde Maka Ska Shoreline Repairs
MPRB has funding allocated to address the shoreline instability at Bde Maka Ska as well as at Lake Harriet. Over the last few years, the condition of the shoreline has […]
Timeline
Milestones (anticipated project schedule by month/season)
2026
Winter: Analysis and Feasibility Study; Permitting Evaluation Phase
Spring: Design Development Phase
Summer: Construction Document Phase
Fall: Construction commences
2027
Spring/Summer: Construction complete
Get Involved
Subscribe to Email Updates
Enter your email to receive updates about meetings, events and more.
Upcoming Meetings
There are currently no meetings scheduled.
Background & Funding
Background
The extents of the shoreline degradation are large, beginning near West 36th Street and extending north beyond W 32nd Street. A few years ago, a small section of shoreline north of W 36th Street was re-established and the adjacent walking path realigned to address shoreline de-stabilization issues. To date some of what was done remains intact, but portions of the shoreline have already eroded.
Portions of Bde Maka Ska shoreline have Works Project Administration (WPA) walls that were built in the early 1940’s, those areas being along the northeast and southeast sections of the lake. The remaining shoreline sections are either public beach areas or have vegetation planted along the edges. In certain areas large stones were placed along the slope presumably to stabilize areas that had started to erode at one point. An 8-foot-wide walking path and 10-foot-wde bicycle path ring the lake. The walking path is located nearest the lake, its distance from the water’s edge varying depending on how much room there is.
Funding
Current project funding includes Met Council regional funding and additional outside funds
Park Board Announcements
There are no announcements at this time. Please check back soon.





