Playground Installation Nearly 75% Complete.

Construction continues to move forward. This week, the sod for the athletic field is being installed. Site concrete, including the new Franklin Ave. sidewalk, is nearly 100% complete. The new picnic pavilion will be installed over the winter.

Construction fencing will remain in place over the winter to give the grass as much of a chance to establish before the park re-opens during the spring/summer of 2019.