Curb and gutter is 90% complete; paving expected to begin in November

Reconstruction of the pay parking lot at Parade Park is on schedule. The old pavement has been removed and curb and gutter installation is 90% complete.

Paving is expected to occur in November. Please follow marked signage for sidewalk and trail detours.

This project includes the full reconstruction of the parking lot, base, stormwater treatment and parking lot entry/exits. Parking is still available in the adjacent lot to the east or in the City of Minneapolis’ Vineland Place Ramp next to the Walker Art Center.

The Minneapolis Park and Recreation Board appreciates the public’s patience while the parking lot is reconstructed.