Currie Park construction update

Thanks for your interest in the improvements project at Currie Park!

  • Site demolition and excavation is nearly 100% complete.
  • Rough grading of the overall site is nearly 100% complete.
  • The construction contractor anticipates completing the foundation for the new restroom building before winter, allowing construction of the building over the winter.
  • With construction having begun in September, the project is planned to be complete by late summer 2020, barring delays due to weather or construction.

Nearby parks and recreation facilities

During construction, we hope you can enjoy other parks and recreation facilities in the area.
Get details on what is available by using the map below – or watch a short video on Facebook or YouTube.

Photo of Currie Park's cleared wading pool.

Above: The wading pool has been cleared to make way for the new splash pad (concept image below) and restroom building.

Concept art of the future splash pad.


Map: MPRB facilities open during Currie Park construction

Map of MPRB facilities open during the construction.


Back to Project Page