Construction Update – July 13, 2015

Veit & Company is continuing with the removal of built items at the top of the slope to create the space needed for an earthen “bench” which will be used as access to drill micropiles into the bedrock below for retaining wall #3. The tower crane at the base of the slope will set up July 23-24. Retaining wall#3 will be constructed first, then wall #2.  These two walls will do most of the work to stabilize and retain the slope.