Status

Current Phase: Pre-Design
Construction Timeframe: Fall 2019

Weren’t able to attend the 11/5 Open House?

You can now view the Parking Lot Reconstruction Concept Plan online. (The PDF is under Key Documents now.) Sign-up for future project updates on the project page because future updates will not go to the full District 4 email list and only to the project list. Back to Project Page

Open House for Parade Park Parking Lot Reconstruction project scheduled November 5

The pay parking lot at Parade Park is scheduled to be fully reconstructed in 2019. Minneapolis Park and Recreation Board (MPRB) Planning and Customer Service staff are hosting a project open house on Monday, Nov. 5, 4-6 pm in the lobby of Parade Ice Garden, 600 Kenwood Parkway. Open House attendees will have a chance to learn about the […]

See All Project Activity

Project Milestones

Winter 2018/2019

  • Design and Construction Documents

Summer 2019

  • Bidding

Fall 2019

  • Construction

Subscribe to Email Updates

Enter your email to receive updates about meetings, events and more.

Upcoming Meetings

There are currently no meetings scheduled. Check back or enter your email address above to subscribe and get notified of new meetings.

Parade Park History


The east portion of the Parade Parking Lot was reconstructed with Minneapolis Sculpture Garden project. The remainder of the parking lot will be reconstructed through this project.

The project is funded through 2018 ($600,000) and 2019 ($600,000) Enterprise Funds (pending the Board approval of the 2019 Budget).