Project Location
Project Manager
Cliff Swenson
Phone: 612-230-6473
Email: cswenson@minneapolisparks.org
Subscribe to Email Updates
Correo Electrónico: preguntas@minneapolisparks.org
Email: suaalo@minneapolisparks.org
Key Documents
- Elliot Park Improvements – Skate Park and Athletic Field Lighting Survey
- Elliot Skate Plaza [PDF]
- Elliot Skate Park Model [PDF]
- Elliot Park – Field Lighting Plan Final [PDF]
- Elliot Skate Plaza Updated Design Illustrations and Renderings [PDF]
- Elliot Skate Plaza Updated Design Planset [PDF]
Status
Current Phase: Completed
What's New
Celebrate the new Elliot Park Skate Plaza on August 6!
Largest skate park in Minneapolis park system is open!
Final phase of construction begins
Elliot Park will be home to largest skate park in Minneapolis park system when it opens this summer
Construction begins soon on upgraded skate park at Elliot Park!
Skate park will open in late fall or spring 2021; connections for new park lighting will cause power outage on July 20-21
Timeline
Project Milestones
- May 6 – May 15: Community Input
- May 15 – June 6: Elliot BLU review
- June 12: MPRB Design and community review period
- Fall: Field and Pedestrian Lighting Out to bid; Skate Plaza Design Development and Grant Writing for Additional Funds
- Winter: Anticipated Field and Pedestrian Lighting Bid Award; Grant Award Notices Due For Skate Plaza
- Anticipated 2020 construction
Get Involved
Subscribe to Email Updates
Enter your email to receive updates about meetings, events and more.
Upcoming Meetings
Background
These updates are the second phase of the athletic field update project. the majority of the skatepark plaza slab was completed along with the field construction.