Spring 2019 Project Update

The Boom Island-Nicollet Island Bridge reopened last November after an extensive repair project revitalized the 118-year-old structure. Beginning next week (the week of April 8, 2019) workers will be onsite to perform remaining work not completed in 2018. This includes site grading and turf establishment, concrete abutment work, paint touch-ups, and electrical work. The follow-up […]

Bridge rehab is nearing completions and is expected to reopen next week (week of 11/19)

Minor work will remain for the contractor in the spring of 2019 including, site restoration and seeding, concrete abutment surface repair and paint touch-ups. A Grand Opening celebration will be scheduled next year as well. Back to Project Page

September Project Update

Recent work on the Boom Island-Nicollet Island Bridge rehabilitation project includes sandblasting and repainting of the bridge substructure, with deck installation scheduled to begin next week.  Unfortunately, significant material delivery delays and construction staging challenges have pushed back expected project completion to early November. All efforts are being made to reopen the bridge as soon […]

August Project Update

The Boom Island-Nicollet Island Bridge rehabilitation project is making good progress, although long lead times for steel and timber decking did cause some delay. The bridge is still expected to reopen this fall, likely in early October. Steel repairs continue this week with sandblasting and painting of the lower steel structure, followed by deck installation on […]

July Project Update

The Boom Island-Nicollet Island Bridge rehabilitation project is making good progress, although long lead times for steel and timber decking has caused some delay. The bridge is still expected to reopen this fall, likely in October. Steel repairs are currently taking place at the site of the bridge. Please continue to follow the posted pedestrian and […]

Onsite work slows for steel fabrication

The Boom Island-Nicollet Island Bridge rehabilitation project is making good progress and the bridge is expected to reopen this fall.  Onsite work will slow for a few weeks while steel necessary for structural repairs is fabricated offsite. Please continue to follow the posted pedestrian and bike detours and stay out of the construction area. The […]

Bridge closes for the Summer Beginning May 21

Bridge will be closed for repairs late May-September The Boom Island-Nicollet Island Bridge rehabilitation project is scheduled to begin on Monday, May 21, 2018. Work is expected to be complete by September 7, 2018.  During construction, the pedestrian and bicycle trail bridge connecting Boom Island/BF Nelson Park to Nicollet Island will be closed to all […]

Revised design presented to Heritage Preservation Commission on April 18

The Minneapolis Park and Recreation Board (MPRB) presented a revised design for the Boom Island-Nicollet Island Bridge Repairs project to the Minneapolis Heritage Preservation Commission (HPC) on April 18, 2017. The presentation was not part of a public hearing and no HPC approval was requested. The revised project design was created after an MPRB application for a certificate of appropriateness to […]

Boom Island-Nicollet Island Bridge Repairs Update

Project is being revised to reflect Heritage Preservation Commission findings The Minneapolis Park and Recreation Board (MPRB) is revising the Boom Island-Nicollet Island Bridge Repairs project after the Minneapolis Heritage Preservation Commission (HPC) denied an MPRB application for a certificate of appropriateness to allow rehabilitation and alterations to the bridge. The original MPRB plan called for the removal of deteriorated steel […]

See the November 30, 2016 Study Report

On November 30, 2016, staff presented a Study Report on the progress of the Boom Island-Nicollet Island Bridge Repairs project. See the 11/30/16 Study Report [PDF].