Linden Hills Park Playground project continues with second phase

New play equipment ordered for the play area for 2-5 year-olds

The Minneapolis Park and Recreation Board is entering the second phase of playground improvements at Linden Hills Park.

During Phase 1 (February 2020-August 2021), funds for new play equipment were reduced due to the cost of drainage work required in and near the playground. Some funds were recouped by using shrubs instead of fencing, and a “Cozy Dome” playground climber was ordered for the 2- to 5-year-old play area.

During Phase 2, MPRB will work with Linden Hills Neighborhood Council (LHiNC) and the community to:

  • Raise funds for additional play equipment
  • Select additional play equipment that meets safety guidelines
  • Install the “Cozy Dome” climber and any other equipment in spring 2022

Please read the Linden Hills Playground Phase 2 Q&A for more details.