Van Cleve Recreation Center roof replaced.
2022
April 2021
ROOF REPLACEMENTS
- Logan Recreation Center’s roof was completed in late February
- Cavell Park’s restroom building had its roof replaced, along with the non-brick portions of its siding, in a project completed over the winter.
Project Update: May 20, 2019
Luxton Recreation Center: replacement of roof and siding replacement is planned for September, with completion in November.
2018 projects:
- Whittier, Longfellow and Brackett recreation center: roof replacement projects were completed.
- Logan Recreation Center – project on hold due to an unsuccessful bidding process.
These projects are funded by the 20-Year Neighborhood Park Plan (NPP20), a long-term initiative that reverses years of under-funding in neighborhood parks.
October 2018: Roof replacements
Brackett Recreation Center has a brand-new roof, and the replacement at Longfellow is well underway, with the gym portion of the building complete.
Project Update: May 10, 2018
Whittier Recreation Center: construction begins June 11; expected completion in late August. During roof replacement for the recreation center gym, the gym, wading pool and part of the playground area will be closed; the rest of the recreation center and the park will remain open.
Longfellow Recreation Center: construction begins August 13 to replace flat roof; repair shingle roof; repair structural roof beam
Logan Recreation Center: construction begins August 6 and is expected to be complete in mid- to late October
Brackett Recreation Center: construction expected in fall 2018
Project Update: February 13, 2018
North Minneapolis
- Northside Service Center: roof replacement complete
- Willard Park restroom building: roof replacement on hold
Northeast/southeast Minneapolis
- Logan Recreation Center: design for new shingle and flat roofs is underway, with construction expected in late summer 2018
- Beltrami Center: roof replacement complete
South Minneapolis
- Longfellow Recreation Center: replace flat roof, repair shingle roof, repair structural roof beam
- Brackett Recreation Center: design for a roof replacement is underway, with construction expected in fall 2018
Southwest Minneapolis
- Whittier Recreation Center: construction on the replacement for the gym roof is expected in summer 2018
Project announcement: April 12, 2017 - Repairs and replacements at six facilities
The buildings below are among those ranked as having a critical need for roof repair or replacement, based on preliminary inventory reports.
Locations
North Minneapolis
- Northside Service Center: replace roof
- Willard Park restroom building: replace roof
Northeast/southeast Minneapolis
- Logan Recreation Center: replace shingle roof, repair flat roof
- Beltrami Center: replace roof
South Minneapolis
- Longfellow Recreation Center: replace flat roof, repair shingle roof, repair structural roof beam
Southwest Minneapolis
- Whittier Recreation Center: replace recreation center and gym roofs